Architectural
Fee Calculator
|
|
|
|
|
|
|
|
|
|
|
|
|
Our fee is
calculated as follows: Total square meters multiplied by estimated building
cost giving us the Contract
Price
|
|
|
|
|
A sliding
scale is applied to the Contract Price to arive at the cost of the full
architectural service.
|
|
|
|
|
|
|
|
|
|
|
|
Total Square
Meters
|
|
Estimated Building Cost
|
|
Contract Price
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Enter total
square meters above.
|
|
Enter
estimated building cost above.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total
Professional Fee.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Please note that this fee is only an estimate and is subject to
change.
|
|
|
|
|
(Stages 1 to
5 as prescribed by SACAP)
|
|
|
|
|
|
|
|
|
|
|
|
Schedule of
payments:
|
|
Amount:
|
|
Percentage of
work done:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Deposit:
|
|
|
|
|
|
|
|
|
A deposit is required before
|
|
|
|
|
|
|
|
|
work can commence.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Design:
|
|
|
|
|
|
|
|
|
After the acceptance of the design,
|
|
|
|
|
|
|
an additional 35% of fee is due.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Municipal
Drawings:
|
|
|
|
|
|
|
|
|
Prior to submission of municipal
|
|
|
|
|
|
|
drawings another 15% is due.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Working Drawings & Technical Document Phase:
|
|
|
|
|
|
|
|
|
A further 25% is payable on
|
|
|
|
|
|
|
finalisation of these documents
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Supervision/
project facilitation
|
|
|
|
|
|
|
|
|
Supervision/ project facilitation is
|
|
|
|
|
|
|
done over the construction
|
|
|
|
|
|
|
period and is divided into the
|
|
|
|
|
|
|
amount of construction time.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|